Requirements
Option 1. Transit-Served Location (1–4 points)
Locate any functional entry of the project within a ¼-mile (400-meter) walking distance of existing or planned bus, streetcar, or informal transit stops, or within a ½-mile (800-meter) walking distance of existing or planned bus rapid transit stops, passenger rail stations, or commuter ferry terminals. The transit service at those stops and stations must meet the minimums listed in Table 1. Planned stops and stations may count if they are sited, funded, and under construction by the date of the certificate of occupancy and are complete within 24 months of that date.- For each qualifying transit route, only trips in one direction are counted towards the threshold.
- If a qualifying transit route has multiple stops within the required walking distance, only trips from one stop are counted towards the threshold.
Table 1. Minimum daily transit service
Weekday trips | Points |
---|---|
72 | 1 |
144 | 2 |
250 | 3 |
360 | 4 |
Option 2. Pedestrian Access (1–4 points)
Show that the project has an attendance boundary such that the specified percentages of dwelling units are within no more than a 3/4-mile (1200-meter) walking distance (for grades 8 and below, or ages 14 and below), and 1 1/2-mile (2400-meter) walking distance (for grades 9 and above or ages 15 and above) of a functional entry of a school building. Points are awarded according to Table 2.Table 2. Points for dwelling units within walking distance
Percentage of dwelling units in attendance boundary | Points |
---|---|
50% | 1 |
60% | 2 |
70% or more | 4 |
What does it cost?
Cost estimates for this credit
On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.
Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.
This information is also available in a full PDF download in The Cost of LEED v4 report.
Learn more about The Cost of LEED v4 »Frequently asked questions
See all forum discussions about this credit »Addenda
"Table 1. Minimum daily transit service"
2. Within the fourth item in the bulleted list of criteria, insert "for Path 1" after "Privately-run shuttles are only acceptable"
3. Within the heading for Table 1 insert "public" between "daily" and "transit"
4. After the paragraph beginning "If existing transit service..." insert the following new language:
OR
Path 2. Access to Project-sponsored Transit Service
Commit to providing year-round transit service (vans, shuttles, buses) for regular occupants and visitors that meets the minimums listed in Table 2, Service must be guaranteed for at least 3 years from the project’s certificate of occupancy.
Within the project boundary, provide at least one transit stop shelter at each transit stop within a ¼-mile (400-meter) walking distance from a functional entry of the project. A building lobby is allowed instead of shelter if the transit stop is visible from inside and located no greater than 200 feet (60 meters) walking distance from the transit stop.
• For each qualifying transit route, total trips (inbound and outbound) are counted towards the threshold.
• If a qualifying transit route has multiple stops within the required walking distance, only trips from one stop are counted towards the threshold.
• Only directly accessible trips within the specified distances are allowed. Trips available from connected transit facilities do not contribute to the minimum trips under Path 2.
Table 2. Minimum daily project-sponsored transit service
Total daily trips Points
30 1
45 2
Provide a guaranteed ride home program for employees who have carpooled, taken transit, walked, or cycled to work but require alternative transportation home for emergencies or unscheduled overtime.
Documentation toolkit
The motherlode of cheat sheets
LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.
Get the inside scoop
Our editors have written a detailed analysis of nearly every LEED credit, and LEEDuser premium members get full access. We’ll tell you whether the credit is easy to accomplish or better left alone, and we provide insider tips on how to document it successfully.
© Copyright U.S. Green Building Council, Inc. All rights reserved.
Requirements
Option 1. Transit-Served Location (1–4 points)
Locate any functional entry of the project within a ¼-mile (400-meter) walking distance of existing or planned bus, streetcar, or informal transit stops, or within a ½-mile (800-meter) walking distance of existing or planned bus rapid transit stops, passenger rail stations, or commuter ferry terminals. The transit service at those stops and stations must meet the minimums listed in Table 1. Planned stops and stations may count if they are sited, funded, and under construction by the date of the certificate of occupancy and are complete within 24 months of that date.- For each qualifying transit route, only trips in one direction are counted towards the threshold.
- If a qualifying transit route has multiple stops within the required walking distance, only trips from one stop are counted towards the threshold.
Table 1. Minimum daily transit service
Weekday trips | Points |
---|---|
72 | 1 |
144 | 2 |
250 | 3 |
360 | 4 |
Option 2. Pedestrian Access (1–4 points)
Show that the project has an attendance boundary such that the specified percentages of dwelling units are within no more than a 3/4-mile (1200-meter) walking distance (for grades 8 and below, or ages 14 and below), and 1 1/2-mile (2400-meter) walking distance (for grades 9 and above or ages 15 and above) of a functional entry of a school building. Points are awarded according to Table 2.Table 2. Points for dwelling units within walking distance
Percentage of dwelling units in attendance boundary | Points |
---|---|
50% | 1 |
60% | 2 |
70% or more | 4 |
In the end, LEED is all about documentation. LEEDuser’s Documentation Toolkit, for premium members only, saves you time and helps you avoid mistakes with:
- Calculators to help assess credit compliance.
- Tracking spreadsheets for materials purchases.
- Spreadsheets and forms to give to subs and other team members.
- Guidance documents on arcane LEED issues.
- Sample templates to help guide your narratives and LEED Online submissions.
- Examples of actual submissions from certified LEED projects.